I find that one of the most common mistakes teams make is to use the
term "velocity" to refer to both
--the number of points (or ideal days) finished in a sprint
--the amount of planned work completed in a sprint
It is far more useful to use velocity to refer to the amount of
points finished in a sprint. The amount of work planned in a sprint
will be relatively constant sprint to sprint. This is essentially the
Y (vertical) intercept of a sprint burndown chart. If you need a term
for that call it "capacity." The tough concept for some teams to get
is that capacity (# of hours of work planned into a sprint) isn't
clearly correlated to the # of hours worked in a sprint. To make it
simple, consider me a team of one doing a one-week sprint. I will
work 40 hours this week. If I'm a perfect estimator (impossible) I
can say "I'll answer email for 20 hours this week (I wish!) and spend
20 developing; let me pull in 20 hours of work during sprint
planning." However suppose I'm not perfect and that my backlog items
have some uncertainty. Over time I may find that when I see a pile of
work and say "that's 15 hours" that this is the amount that perfectly
fills up my 40 hour workweek. I may get 25 hours of time on task to
do what I called 15 or I may get the 15 done in 12. It won't matter.
What matters is that what I call 15 fills up my week. That's how to
plan sprints and to work with capacity.
Thursday, December 21, 2006
Velocity and more
Here is nice article from Mike Cohn about Velocity